Here are some options below:įreeze 15 days and 20 hours total work: either 16% or 17% resource allocation (running tests on MS Project 2010 standard does not handle fractional % allocations – comes up with 17%)įreeze 30% allocation and 15 days: 36 hours workįreeze 30% allocation and 20 hours: 8.33 days duration You will need to 'freeze' some combination of your Duration, Work, % Resource Allocation and allow the other to ‘float’ in the calculation process. 36 hours of work yielded from the 30% allocation. There is a mismatch in your requirement between the 20 hours of work vs. Considering the basis of your question as your requirement:Ģ0 hours’ work required for a task, over 15 days duration with 30% resource allocation.ģ0% of a single day is 2.4 hours, times 15 days = 36 hours and not 20 hours.